When can RERA cancel a real property project entirely?

Under Article (23) of Resolution No. (6) of 2010, RERA can cancel a project if the developer fails to start construction without a valid justification. Other grounds include a lack of genuine intention to implement the project or the bankruptcy of t…

The full explanation

Under Article (23) of Resolution No. (6) of 2010, RERA can cancel a project if the developer fails to start construction without a valid justification. Other grounds include a lack of genuine intention to implement the project or the bankruptcy of the developer. RERA issues a decision based on a technical report and must notify the developer. Following cancellation, the developer is legally required to refund all payments received from purchasers within sixty days.

This is general information from the website library. Confirm current rules, fees and property details with the relevant authority before acting.